Road Resurfacing – Phase I
The list below is the roads are being included in Phase I of the road program. AF Damon of Brookhaven is the low bidder and was awarded the project. Start dates will be provided as soon as they are known.
Street | Cross Streets | Length (mi) | Length (ft.) |
Width (ft.) |
Area (sy) |
Wearing Course (tons) |
Milling (sy) | Base/ Trench Repair (sy) |
Base Bid | ||||||||
Palmers Lane | Copples – Osbourne | 0.20 | 1050 | 22 | 2820 | 290 | 2820 | 600 |
Hawthorne Road | E. Rose Valley – Palmers | 0.20 | 1065 | 24 | 3120 | 320 | 3120 | 600 |
Osborne Lane | E. Rose Valley – Palmers | 0.20 | 1080 | 22 | 2900 | 300 | 2900 | 600 |
Scott Lane | Windsor – end | 0.11 | 575 | 24 | 1680 | 170 | 1680 | |
Brent Road | Governors – Bullens | 0.34 | 1770 | 27 | 5840 | 590 | 5840 | |
Maple Avenue | Elm – End | 0.08 | 410 | 24 | 1200 | 130 | 1200 | |
Maple Road | Ryanard – Media | 0.11 | 555 | 20 | 1350 | 140 | 1350 | |
Pine Road | Blakeley – Ryanard | 0.10 | 550 | 23 | 1540 | 160 | 1540 | |
Mulberry Lane | Truepenny – Twp Line | 0.19 | 985 | 36 | 4330 | 440 | 4330 | |
Ronaldson Street | Forrest – Allen | 0.07 | 360 | 23 | 1010 | 110 | 1010 | |
Twyckenham Road | Luckie – Bent | 0.19 | 1010 | 30 | 3700 | 380 | 3700 | |
Glenwood Avenue | Oakland – Manchester | 0.09 | 500 | 18 | 1100 | 120 | 1100 | |
Morris Lane | Meadow – Burning Tree | 0.12 | 655 | 25 | 2000 | 210 | 2000 | |
Bent Road | All | |||||||
Waterford Circle | Waterford Way – End | 0.07 | 345 | 27 | 1130 | 120 | 1130 | |
Allen Street | Wallingford – Ronaldson | 0.06 | 340 | 20 | 830 | 90 | 830 | |
Ronaldson Street | Allen – end | 0.04 | 200 | 23 | 560 | 60 | 560 | |
Governors Drive | Cameron – Chester Rd | 0.11 | 580 | 35 | 2480 | 250 | 2480 | |
Parkview Slope | Chestnut – Maple | 0.09 | 455 | 16 | 880 | 90 | 880 | |
Avondale Road | Martroy – Copples | 0.15 | 800 | 20 | 1950 | 200 | 1950 | |
Avondale Road | Copples – Cell Tower | 0.16 | 860 | 20 | 2100 | 220 | 2100 | |